PDP Executive Monitoring Dashboard — Punjab Development Program — A development project monitoring system for 52 cities in Punjab

The PDP Executive Monitoring Dashboard is the development project monitoring system of the Punjab Development Program (PDP), which is building sewerage, storm-water drainage and disposal works in 52 cities across 25 districts of Punjab. Field officers file each day’s progress from an Android app that works without signal; the server stamps every photo as evidence and rolls progress up by weight, not by average. Since July 2026 NexGenix has re-engineered and operated the system for the Program Management Unit (PMU), after migrating it to the Government of Punjab’s own server.

The original platform was developed by Technology Hive (TechHive). NexGenix took it over in July 2026, migrated it to the Government of Punjab’s own server, and has re-engineered and operated it since.

Program Management Unit (PMU), Punjab Development Program — LG&CD Department, Government of Punjab
  • Node.js 20
  • Express
  • MySQL 8
  • REST API
  • JWT Auth
  • Leaflet
  • Chart.js
  • PDFKit
  • jsPDF
  • SheetJS
  • Sharp
  • React Native
  • Expo
  • PM2
  • Linux
PDP Executive Monitoring Dashboard command centre: program scope, financial overview and execution by criticality across 52 Punjab cities
PDP command centre on a phone, with progress KPIs stacked for a small screen

By the numbers

Program cities
52
Districts
25
Residents in program cities
7M
Contract packages
394
Field photos on record
33,000+
Approved program cost
PKR 308bn

As of November 2026. Program figures come from the PDP Executive Monitoring Dashboard; the photo count grows every day.

The full story

The Punjab Development Program, and why it needs a project monitoring system

The Punjab Development Program (PDP) is rebuilding the parts of a city most residents never see: underground storm-water tanks, storm drains, disposal stations, sewer lines and the roads restored above them. As of November 2026 it covers 52 cities in 25 districts, home to about 7 million people, through 394 contract packages with an approved cost of about PKR 308 billion. The Local Government & Community Development (LG&CD) Department, Government of Punjab, runs it through a Program Management Unit (PMU).

A program of that shape produces thousands of small facts every day: a few hundred feet of drain lined in one city, a tank slab poured in another, a disposal station waiting for machinery in a third. The PMU has to turn those facts into a figure it can stand behind, for each structure, each city and the program as a whole. Field officers report from sites that often have no mobile signal, and the Department’s leadership needs the result the same day, not at the end of the month.

That is the job of the PDP Executive Monitoring Dashboard: a development project monitoring system made of a web platform for the PMU and the Department, and an Android field app for the officers on site.

The problem: progress figures without evidence

Before the platform, city progress reached the PMU as spreadsheet figures. A typed percentage could not be traced to a photograph, a date or the officer responsible for it, so every review began with the question of whether the number was real. Reconciling the figures for a briefing was manual work, repeated every time leadership asked for an update.

There was a quieter problem in the arithmetic. Averaging percentages treats a small tank and a large underground tank as equal, and a short drain the same as a long one. In a worked example from the system’s manual, the plain average of one city’s tank progress comes out at 91.33%; weighting each tank by its storage capacity gives 75.70%. A monitoring system that averages can report a program as nearly finished while most of its capacity is still being built.

The Department also needed the figures in its own shape. Officials brief from their own slide format, so a useful system had to produce that format directly, not hand them one more dashboard to transcribe.

July 2026: taking over a live system and moving it to the Government’s own server

The original platform was developed by Technology Hive (TechHive). In July 2026 NexGenix took it over. We audited the code, the database and the field app, documented how each figure was produced, and planned the system’s move onto infrastructure the Government controls.

On 24 July 2026 the application, its full database and every field photograph moved to the Department’s own server on the Government of Punjab network, under the Department’s existing secure domain. Field reporting dipped for a single day and was back to normal the next. Older versions of the field app moved themselves to the new address through the app’s own update prompt, so no officer had to reinstall anything.

The Department’s server is locked down, so we also shipped the complete Android build toolchain to it. New versions of the field app are built on Government infrastructure and distributed from the Department’s own domain, and a minimum-version check on the server stops outdated apps from filing.

What we re-engineered: weighted, evidence-backed progress measurement

We rebuilt progress measurement as a four-stage weighted roll-up. Each structure reports its own progress. Structures roll up into a component weighted by what they hold or carry: gallons of storage for tanks, wet-well volume for disposal stations, running feet for drains. Components roll up into the city using weights the PMU sets, and cities roll up into the program weighted by approved cost. Positions are calculated, not stored, so the command centre, the reports and the published data feed always show the same figure.

Every filing is checked before it counts. The server confirms that the officer is assigned to the city, that the quantity stays within the structure’s scope, that progress does not fall below the verified position, that the safety record is complete and that the app is a current version. A refused filing writes nothing. The verified position works as an authorised floor: only the Secretary or a system administrator can restate it, and that change is recorded.

Where progress can be measured rather than typed, it is. Officers draw the executed sewer, drain or pavement alignment on a map over the approved design drawings, and the length comes from the line itself. Pavement counts each stretch once, so overlapping drawings are never double-counted. A nightly snapshot of every position feeds S-curve tracking of planned against actual progress toward the program’s 2027 target.

Engineering highlights: an offline field app, photo evidence and a faster GIS map

The PDP Field Progress app is built in React Native and is at version 2.9.0 as of November 2026. Filings, photos and returns queue on the phone when there is no signal and sync when it comes back; each carries a unique reference, so a retry never files twice. The app shows each officer today’s plan for their cities, asks for the people, machinery and health-and-safety checklist on site, and offers a “no activity today” declaration with a reason and a location, so silence is reported rather than assumed.

Every photograph filed from the app is stamped on the server, not on the phone. The server burns a banner into the image with the program, city, officer, location, Pakistan time and an eight-character verification code derived from a SHA-256 hash of the officer, capture time and position, so any photo can be checked against the record it came from.

On the web side we cut the program map’s first load from 37 MB of geometry to 9 MB, added the PDP Live wall that shows field filings as they arrive, and built a one-click daily brief that reproduces the officials’ own slide format as a PDF. Every report also exports to Excel, and the map filters run from division to district, tehsil and municipal committee.

A Report Center groups the standing reports the PMU works from: structure-wise and city-wise progress, a safety audit of health-and-safety compliance, a field-officer compliance report with a chase list of anyone who has not filed, and one-click program and city reports as PDFs. Each reads the same weighted positions, so a figure in a report always matches the one on screen.

How the monitoring system runs today

As of November 2026 the platform serves six roles (system administrators, PMU administrators, the Department’s IT Wing, the Secretary and executives, a read-only data role, and field officers limited to their assigned cities) through 11 modules and 27 web pages backed by about 210 API endpoints, roughly 52 database tables and about 128,000 lines of application code on Node.js 20, Express and MySQL 8.0. More than 33,000 field photographs are on record, and authorised Government systems read the same figures through a read-only data feed whose keys can be limited to specific cities.

NexGenix operates the system day to day. Every change is a single approved item: it is committed to version control, a database backup is taken before it goes live, and it is checked on the live system afterwards. We released 75 improvements in the first month and have kept shipping since, including weighted physical progress, the PDP Live wall, municipal committee boundaries and photo moves between structures. The field app went through thirteen builds between August and November 2026.

For the PMU, the result is a progress figure for every structure, every city and the whole program that arrives with its own evidence, on a system that runs on infrastructure the Government controls.

How it works

How a day’s work becomes a verified figure

From the site to the Secretary’s desk, every number passes through the same five steps.

  1. File from the field

    A field officer records the day’s quantity, people, machinery, safety checklist and photos in the Android app, online or offline.

  2. Check and stamp the evidence

    The server checks city, scope, verified floor, safety record and app version, then burns an evidence banner into each app photo.

  3. Weighted roll-up

    Progress rolls up from structure to component, city and program, weighted by capacity, length and approved cost.

  4. Dashboards and map

    The command centre, program map, PDP Live and S-curve all read the same calculation the moment it changes.

  5. Daily brief

    One click produces the daily brief in the officials’ own slide format as a PDF, with Excel exports for every report.

System tour

How it works, screen by screen

  1. Command centre: the whole program on one screen

    The executive dashboard opens on the program’s headline figures: cities, contract packages, physical and financial progress, and completed tanks, drains, disposal stations, sewer and pavement. Program scope, the financial overview, execution by criticality and city-by-city progress follow, and one city filter re-scopes the entire page.

    • Physical and financial progress side by side
    • Execution by criticality for critical and non-critical works
    • Download Report and Daily Report one click away
  2. Program map: every city and structure on GIS

    A map of Punjab plots every program city, with a progress summary and a city search. In the full map view, filters run from division to district, tehsil and municipal committee, and each city opens its own intervention plan with tank, drain, disposal and park markers and the sewer and pavement lines drawn from the field.

    • Division, district, tehsil and municipal committee filters
    • Per-city intervention plans as map layers
    • Street, satellite and hybrid basemaps
  3. PDP Live: field filings as they happen

    A big-screen wall for the PMU’s operations room. Each filing from the field app appears as it arrives, next to today’s submissions, photos, active officers, cities and locations, and the day’s progress for tanks, drains, disposal stations, sewer lines, pavement and pipe production.

    • Live feed of field filings with photo thumbnails
    • Cities active today on a map
    • Optional sound alert for every new filing
  4. Field gallery: the photo record behind every figure

    More than 33,000 site photographs as of November 2026, each tagged with its city, structure and stage (before, during, after or safety). The gallery is paged on the server with generated thumbnails, so it stays fast as the archive grows.

    • Filters by city, structure, category and date
    • Grid and list views with a full-size viewer
    • Server-side paging with generated thumbnails
  5. Structure progress: weighted, not averaged

    The structure view shows the program’s weighted progress, the weight given to each structure type and a card for every city with its own progress ring and a breakdown by structure. The PMU sets the weights, and they must add up to 100.

    • Weighting framework visible to every reviewer
    • A progress ring and breakdown for each city
    • The same calculation as the dashboards and reports
  6. City-wise report: progress by city, district and region

    A dense progress matrix for reviews: each city’s tanks, drains, disposal stations, sewer, pavement and parks, with physical and financial progress side by side. Tabs switch the same roll-up to district and region level, and the table exports to Excel.

    • City, district and region tabs
    • Physical and financial progress for each city
    • Excel export for review packs

Timeline

  1. July 2026

    Takeover and audit

    NexGenix takes over the platform originally developed by Technology Hive and audits its code, database and field app.

  2. 24 July 2026

    Moved to the Government’s own server

    The application, its database and every field photo move to the Department’s server. Field reporting dips for one day only.

  3. August 2026

    First month: 75 improvements

    An executive redesign of the command centre, the program map cut from 37 MB to 9 MB, and 101 pages of system documentation for the PMU.

  4. September 2026

    Hardening and new map layers

    Municipal committee boundaries and revised design drawings reach the map, and the last spreadsheet fallback for city figures is retired.

  5. October 2026

    PDP Live and the daily brief

    The PDP Live wall, the one-click daily brief, weighted physical progress, a city-wise report and an IT Wing role go live.

  6. November 2026

    Measured, not typed

    Field app 2.9.0 measures pavement restoration from drawn lines. Releases continue as single approved items.

Results: what changed

One defensible progress figure for every structure, city and the program, weighted by capacity, length and approved cost instead of averaged
Every photo filed from the field app carries a banner burned in on the server: officer, location, time and a verification code
Field filing works without mobile signal and syncs later, and a retried upload can never be filed twice
Moved onto the Government of Punjab’s own server on 24 July 2026 with only one day of reduced field reporting
Program map first load cut from 37 MB to 9 MB, so the GIS view opens on ordinary office and field connections
A one-click daily brief in the officials’ own slide format as a PDF, plus Excel exports for every report
Reported progress can only move up from a verified position, which only the Secretary or a system administrator can restate
75 improvements released in the first month after takeover, and steady releases since

Where this approach fits

  • Monitoring and evaluation (M&E) of multi-city development programs
  • Real-time progress monitoring of sewerage, drainage and other civil works
  • Geotagged site photo verification for public works schemes
  • Offline field data collection where mobile signal is unreliable
  • Executive dashboards and daily briefs for departments and PMUs
  • S-curve tracking of planned against actual progress toward a target date
Inside the System
Command centre in dark mode: program-wide KPIs, program scope, the financial overview and execution by criticality.
PDP Live in dark mode, designed for a big screen in the PMU’s operations room.
Photo viewer: a full-size site photo with its structure, city, category and date, and a filmstrip of the photos around it.
Archives: a file manager of every upload, organised by division, with storage use at a glance.
City-wise report in dark mode, with physical and financial progress for each city.
Sign-in page on the Government of Punjab domain, restricted to authorised Department users.

Running a program with the same problem?

Tell us how your department tracks progress or pays contractors today. We reply with a short written plan for your situation, not a sales sequence.

Two systems, one program

Two systems, one program: the contract & IPC payment system

The same PMU pays its contractors through PMIS, the public works contract and payment management system we took over alongside the Dashboard. Where the Dashboard shows what has been built, PMIS decides what each contractor is owed, through an 11-step IPC approval route and a live link to the province’s Financial Management System.

Download the success story

PDP Punjab success story

Both systems in one PDF: the program, what we took over, what we re-engineered and how the systems run today. Ready to attach to a tender or evaluation file.

  • English
  • 4 pages · 1.5 MB
Download PDF

Development project monitoring — FAQs

Questions departments and PMUs ask about the PDP Executive Monitoring Dashboard.

It is software that tracks the physical and financial progress of a development program’s works, site by site and city by city, against plan. The PDP Executive Monitoring Dashboard does this for 52 Punjab cities, combining field filings, photo evidence, weighted roll-ups, maps, S-curves and daily briefs in one system.

Each filing is checked on the server against the officer’s assigned cities, the structure’s scope, a verified floor and a complete safety record. The server then burns a banner into every photo filed from the app with the officer, location, time and a verification code, so each figure can be traced to its evidence.

Yes. The Android app queues filings, photos and returns on the phone and syncs them when the signal returns. Each filing carries a unique reference, so a retry can never file the same work twice. Officers can also declare “no activity today” with a reason and their location.

Because structures differ in size, and an average treats a small tank like a large one. The dashboard weights tanks by storage capacity, drains by length and cities by approved cost. In a worked example, a plain average reads 91.33% while the capacity-weighted figure is 75.70%, which is the honest number.

An S-curve plots cumulative progress over time. Work starts slowly, speeds up, then levels off near completion, so the planned line looks like an S. The dashboard draws a modelled planned curve to the program’s 2027 target and plots actual progress from a nightly snapshot, so slippage shows early.

Technology Hive (TechHive) developed the original platform. In July 2026 NexGenix took it over, migrated it to the Government of Punjab’s own server and has re-engineered and operated it since, including the weighted measurement method, the PDP Live wall, the daily brief and every field-app release since August 2026.

Yes. The PDP Dashboard runs on the Department’s own server under its existing domain, with no third-party cloud, and even its Android app is built on government infrastructure. We can deploy the same way for another department, including on servers with restricted internet access.